Problem

Given set of activities with start and finish time, schedule as many as possible so they do not collide.

i123456
si132363
fi345579

Solution

If ordered on finish time, choose activity with earliest finish time. If ordered on start time, choose activity with latest start time.

here, solution is: { (1,3) , (3,4) , (6,7) } so activities {1, 2, 5}

Use an iterative greedy algorithm that literally tries adding everything.

Complexity

ϴ(n). You just go through all items once and you’re done.